ONLINE COMMUNITY CONSULTATION
Thornholme Field WIND FARM

What's happening?

This page will keep you up to date with what is happening on the project and show you what has been done so far.

Activity Date Detail
Site identification 1st August 2008 Milestone
Initial feasibility studies 1st February 2009 Study
Ecology and ornithology surveys 1st February 2010 Study
Consultation started 1st March 2010 Consultee
Landscape and visual impact assessment 7th June 2010 Study
Request for a Scoping opinion submitted 3rd February 2011 Milestone
Wind monitoring mast application 3rd February 2011 Milestone
Letters to Parish Councils 3rd February 2011 Community
Scoping opinion received 10th March 2011 Milestone
Project newsletter 22nd March 2011 Community
Meeting with Ward and Parish Councillors 22nd March 2011 Community
Press release following Public Exhibition Apr 2011 Community
Public Exhibition 13th April 2011 Community
Met Mast Approved - Press Release 19th April 2011 Milestone
Wind monitoring mast installed 18th May 2011 Milestone
Planning Application Submitted 30th August 2011 Milestone
Planning Application Validated 8th September 2011 Milestone
Typical wind turbine timeline

Typical wind turbine timeline

Home - The Wind Farm - Facts & figures - Why here? - Predicted views - Community benefits - What's happening? - Community - Consultees - Studies - Milestones - The process - Planning - Construction - Operation - About us - Values & history - How we work - Wind energy - FAQ's - Education - Visiting a wind farm - Links - Picture gallery - Contact us - Have your say - Search - Terms, Conditions & Disclaimer

Copyright © 2012 - Wind Prospect Ltd

Content Management System and Database Design BristolContent Management System and Database Design Bristol