This page will keep you up to date with what is happening on the project and show you what has been done so far.
| Activity |
Date |
Detail |
| Site identification |
1st August 2008 |
Milestone
|
| Initial feasibility studies |
1st February 2009 |
Study
|
| Ecology and ornithology surveys |
1st February 2010 |
Study
|
| Consultation started |
1st March 2010 |
Consultee
|
| Landscape and visual impact assessment |
7th June 2010 |
Study
|
| Request for a Scoping opinion submitted |
3rd February 2011 |
Milestone
|
| Wind monitoring mast application |
3rd February 2011 |
Milestone
|
| Letters to Parish Councils |
3rd February 2011 |
Community
|
| Scoping opinion received |
10th March 2011 |
Milestone
|
| Project newsletter |
22nd March 2011 |
Community
|
| Meeting with Ward and Parish Councillors |
22nd March 2011 |
Community
|
| Press release following Public Exhibition |
Apr 2011 |
Community
|
| Public Exhibition |
13th April 2011 |
Community
|
| Met Mast Approved - Press Release |
19th April 2011 |
Milestone
|
| Wind monitoring mast installed |
18th May 2011 |
Milestone
|
| Planning Application Submitted |
30th August 2011 |
Milestone
|
| Planning Application Validated |
8th September 2011 |
Milestone
|